Planning#
Why can't I type a start time?#
Because the times follow the order. You choose each machine's order and the Schedule works out the times from your hours, makeready and ready checks, which is what keeps two jobs from overlapping on one machine. To keep a step from starting before a certain time, pin it, or drop it with ⇧ held where you want it (see Placing and re-planning). To give a step more time, drag its right edge.
Why did a step move later?#
Something before it changed: the step before it on the machine ran over, the job's previous step finished later, downtime was added, or a ready check is still open. Every step's time is worked out again after each change, keeping the order. Started steps and the steps inside the time fence keep their machine and place, but can still start later.
Why is my job still in the tray?#
- It waits for a ready check: look in the tray's Waiting section and at the job's Ready checks tab.
- A step has no machine that can do it: the job panel says "No machine can do this step yet". Add one, or change the route.
- It is On hold: Release it.
- Place all ready leaves jobs with a failed check alone until the check passes.
What does ≈ mean?#
The step's time is an approximation, for example on another press than the job was imposed for. Hover it for the reason. See Machines and capabilities.
Why is the risk Unknown?#
The job has no due date, or a step on the way to its finish has only an approximate time. Give it a due date on the imposition job's Order card or its items' Due property.
Can two people plan at the same time?#
Yes. Each change is small and saved at once, and everyone's board updates within seconds. If the plan changed while you were looking at a preview, the preview asks you to look again before it applies anything.
Jobs and solutions#
Can I schedule work that isn't imposed here?#
Yes. New job on the board adds one job, Import jobs from a CSV adds many, and your own system can send them through the API. Give each your own job number as its reference: a later import or API call with the same reference updates the job, and a scan of that number at the machine finds it. See Adding and editing jobs.
My MIS prints the job tickets. Can operators scan those?#
Yes, when the barcode holds the job number you gave the job as its reference. Scan it in the station's Scan job box: the first scan starts the job's step on that machine, the next one finishes it. See The station.
I changed the solution after the job was scheduled#
If nothing has started, the steps are timed again from the new solution and keep their machines, order and pins. If something has started, nothing changes by itself: the job's panel shows a banner saying the solution changed after production started.
I chose another solution for the job#
The job keeps its place on the board and takes the new solution's steps and times. It doesn't go back to the tray.
I removed the solution, or deleted the imposition job#
If nothing has started, the job leaves the board (back to the tray, or cancelled when the imposition job is gone). If something has started, the job stays, marked, so its history isn't lost.
How do I schedule a reprint?#
Once a job is done, use Put on the schedule in the imposition job's Export menu and confirm Schedule it again as a reprint?: the same imposition job is scheduled again as a new job, and the done one keeps its history. A finished job isn't listed under Imposed, not on the schedule, so Add all never schedules it twice by mistake.
Does the Schedule change due dates or priorities?#
No. They belong to the imposition job (its Order card) and its items. Change them there and the Schedule follows.
How are two passes on an offset press handled?#
When a job needs two passes through the press, the drying time between them is planned as a wait after the print step. The press's time and the next step's start are right; the second pass isn't shown as its own bar.
The floor#
An operator ran a different job than planned#
That's fine: what happens on the floor is always recorded, and the plan follows. See The station.
What if a machine breaks?#
The operator taps Machine down and picks when it should be back. The machine's work moves later and planners are told. See The station.
Who can see and change the Schedule?#
Every team member can see the board, the phone view and the stations, and use the stations. Planning is open to every member unless an admin limits it (see Schedule settings). Machines, hours, routes, ready checks and settings are for team admins.